posted Aug 27, 2013, 6:35 AM by Grant Harris
[
updated Aug 27, 2013, 6:35 AM
]
The IT staff has finished cabling the New Administration/Preschool Building at 2 Blackburn Drive.
- All data lines have been pulled, tested, and labeled. (over 10K ft. of cabling)
- Installed new wall mounted Data cabinet
- Extended the City/School Fiber Network to site
- Install and configured new Gig POE switches
- WiFi has been installed across the building for 100% coverage
- Tested VoIP connectivity to central PBX's
This was a major job and I wanted to thank Tylor Marquis, Joe Brancaleone, and Paul Donovan for making this happen on-time.
Great Job!
Grant Harris IT Operations Manager |
|